When to use it, a subject line, a body you can paste and fill, what to attach, how to word impact, and what not to say.
When to use: a spec item (special grade, HSS size, stainless, weathering steel) has a lead time that threatens the schedule and you need direction or early release.
Subject: RFI [no.] — Long-lead material at [location]: direction needed by [date] to hold schedule
Body:
[Material/section/grade] specified at [location] currently shows [x-week] mill lead time per [supplier(s)]. To meet the erection date of [date], a purchase order must be placed by [date]. Please confirm: (1) the specification stands as written, or (2) direction on the attached alternates. If early material release is available under [contract provision], we request it for this item.
Attach: supplier lead-time quotes (two if you can get them), alternate options with property comparison. Impact wording: work backward from erection date to PO date and show the math — dates are more persuasive than adjectives. Don't say: "we cannot meet schedule" — say what date makes the schedule work and what needs to happen by then. Escalation: elevate from RFI to a schedule-risk line item in the next OAC meeting; long-lead is a project problem, not a steel problem.
Log every one of these. Submission date, needed-by date, response date, what was held, what it cost. That trail is where steel money leaks — and where it’s recovered.
Drafting aid only — not legal advice. Adapt to your contract's notice requirements; your EOR and contract documents govern. Impact/rights wording is a starting point, not a determination.